AI Boom Leaves Networks Waiting 18 Months for Kit

By The Daily Byte ·27 Nov 2026 ·3 min read
Fibre-optic cables and optical networking equipment inside a data centre

The artificial intelligence building boom is driving up the price of optical networking equipment and stretching delivery times to as much as 18 months, network operator RETN has warned, as telecoms companies find themselves competing directly with AI data centres for the same components.

RETN says optical networking equipment prices have risen by around 50 per cent since the start of 2026. Kit that used to arrive within three months now typically takes 12 to 15 months, with some orders taking 18 months or longer. Memory prices have risen four or five times over the past year, The Register noted in reporting the findings on Friday.

Data centres are buying up the network

The findings come from RETN's white paper, 'AI, Connected', published on 9 November. It says network operators and telecoms companies now compete with AI data centres for chips and other components, and that demand is outpacing supply. Raw material shortages, skilled labour shortages, energy constraints, geopolitical tensions and logistical problems are compounding the issue, RETN says.

The paper also warns that carriers made the problem worse for themselves by postponing network upgrades to cut spending. That work has now become unavoidable, RETN says, at the worst possible time.

About 80 to 90 per cent of RETN's AI-related connectivity requests are for private point-to-point links, dark fibre and dedicated interconnections, used to move petabytes of data directly between training clusters. Public internet traffic, by contrast, has seen only a modest contribution from AI so far, according to the report.

Remote sites need carriers years in advance

AI data centres are moving away from populated areas to remote locations, where land, power and water are easier to secure. Hyperscalers are building in the Nordics, where land is affordable, the climate is cooler and renewable energy is plentiful. But remote sites often lack the fibre needed to connect them, and RETN says developers building outside established hubs may need to involve network carriers two to five years before a site opens, against one to two years previously.

Network diversity is now seen as essential, the report says. Where customers were once satisfied with two routes to long-haul destinations, they now expect four or more redundant routes, each avoiding shared physical failure points such as the same ducts or cable routes. A diverse circuit might cost 1,800 euros a month instead of 600 euros, RETN says, but an outage could prove far more costly.

Some developers are prepared to swallow the cost: RETN says a major cloud provider is exploring converting an abandoned factory in Central Europe into a large server farm, despite little existing fibre in the area. The message from the report is that connectivity must be planned alongside power and construction, not left until a data centre is nearly ready to open, and at current lead times, leaving it late may mean waiting more than a year for the kit to arrive.