Angola Begins $164m Solar Plant for Cabinda

By The Daily Byte ·26 Nov 2026 ·3 min read
Cabinda city in Angola

Angola has begun construction of a €142 million ($164 million) solar power plant in its isolated Cabinda province, a project the government says will bring more reliable electricity to more than 180,000 people facing chronic power shortages. Egypt's Elsewedy Electric broke ground on the 90-megawatt-peak facility in Ngoio on 16 November.

The plant is being developed for Angola's state-owned electricity generator, PRODEL-EP, and is scheduled for completion in June 2029. It will pair a 90MWp solar array with 25 megawatt-hours of battery storage, along with a 33/60kV substation and nine kilometres of overhead transmission lines. South African engineering firm Zutari is supervising construction.

A province with power it cannot deliver

Cabinda's electricity problems are not caused by a lack of generation capacity alone. The province had nearly 200 megawatts of installed generation capacity in 2025 but distributed only about 97 megawatts, less than half of the roughly 400 megawatts provincial authorities estimate it needs.

The gap between installed and delivered power points to weaknesses in transmission and distribution networks, which limit how much electricity reaches homes and businesses. Much of the province's existing supply comes from thermal generation, including the Malembo thermal power plant.

The new solar plant is designed to add generation that can be stored and dispatched when needed, easing pressure on the thermal fleet and reducing the province's reliance on fossil fuels.

An exclave cut off from the national grid

Cabinda's geography adds to its energy challenges. The coastal province is separated from mainland Angola by a strip of territory belonging to the Democratic Republic of Congo, which makes connecting it to the national electricity grid difficult. The province has therefore had to rely largely on its own generation capacity.

Alongside the Ngoio solar plant, Cabinda is pursuing a submarine electricity connection from Soyo, a port city on Angola's northern mainland coast. The tender for the subsea section of that link was relaunched in 2026 after an earlier procurement process was cancelled.

The Ngoio project was first authorised in 2022. An initial financing agreement worth €141.8 million was approved that year, followed by agreements with HSBC in 2023, although the government's latest announcement did not specify whether the financing had been finalised.

What the plant will add

At €142 million, the investment is a significant step towards expanding Cabinda's renewable energy capacity, but it will not on its own close the province's supply deficit. Further investment in generation and grid infrastructure will be needed to meet demand, and the solar plant's 90MWp of capacity is only part of the estimated 400MW requirement.

For the more than 180,000 people the authorities expect the plant to serve, the project promises steadier power when it is commissioned in June 2029, after three years of construction. For Angola, it is also a test of whether solar power paired with battery storage can stabilise supply in a province whose grid has long struggled to deliver the power it already generates.