Belgium Offshore Wind Farm Wins €2bn EU Approval

The European Commission has approved a €2.04 billion Belgian state-aid scheme to support the construction and operation of the first offshore wind farm in the Princess Elisabeth Zone in the North Sea. The approval, announced on 10 November 2026, clears the way for Belgium to relaunch the tender for the project.
The wind farm is expected to have a capacity of up to 735 megawatts and to generate up to 2.6 terawatt-hours of renewable electricity a year. The support scheme will run for 20 years and the aid will be awarded through a transparent and non-discriminatory bidding process, with the result expected in the fourth quarter of 2027.
How the support will work
The scheme was approved under the Commission's Clean Industrial Deal State Aid Framework, adopted on 25 June 2025. Support will take the form of a two-way contract for difference: the state tops up income when market prices fall below an agreed level and recovers money when prices rise above it. Unusually, payments will be based on the farm's theoretical capacity rather than the power it actually delivers, a design intended to avoid subsidising production when prices are negative.
The tender will also include prequalification requirements under the EU's Net-Zero Industry Act, designed to diversify supply chains for turbines and components and reduce reliance on non-European suppliers.
A tender relaunched after cancellation
The approval is the final requirement for relaunching a tender that was cancelled in July 2025 because of legal, financial and technical uncertainties, notably around the support mechanism. In July 2026 Belgium adopted a revised tender framework featuring the two-way contract for difference and an extension of the maximum construction period from four to five years.
The newly approved scheme supersedes a previous €682 million support measure authorised by the Commission in September 2024 under the Temporary Crisis and Transition Framework. The wind farm will connect to the Princess Elisabeth Island, an artificial energy hub being built by grid operator Elia about 50 kilometres off the Belgian coast.
The island is designed to gather power from the new wind zone and carry it ashore, and its first phase alone has been reported to cost €3.6 billion, underlining the scale of investment behind Belgium's offshore expansion.
The approval confirms only that Belgium's scheme meets EU state-aid rules. No developer has yet been chosen, and the farm is not yet built or generating electricity. The eventual strike price agreed in the tender will show how much support is really needed.
Sources: Energy Global; Enerdata. Published 16 November 2026.