EU approves €9.5bn Dutch offshore wind aid for IJmuiden Ver Gamma farms

The European Commission has approved a €9.5 billion Dutch scheme to support renewable electricity production from two offshore wind farms in the North Sea, clearing the way for tenders for the IJmuiden Ver Gamma-A and Gamma-B sites.
The Commission announced the decision on Tuesday, 17 November, under EU State aid rules. The Netherlands notified the scheme, known as TOWOZ, to support the two wind farms, which have a combined capacity of 2 gigawatts and are expected to generate up to 7,441 gigawatt-hours of renewable electricity a year. The scheme has a maximum budget of €9.45 billion, and the Commission said the aid would be granted through a transparent and non-discriminatory bidding process.
How the support will work
The scheme covers two offshore wind tenders to be organised before July 2027. Support, if needed, will be paid for 15 years from the start of operations, which is expected in 2032. The tenders offer either a concession payment or a variable premium subsidy, with safeguards such as a bid cap and a claw-back mechanism to prevent overcompensation.
Developers can also bid without subsidy. The Dutch government has said subsidy-free bids will be considered first, with support available only if no bidder offers to build the projects without aid. The projects are expected to avoid 147 million tonnes of CO2 equivalent over their lifetime, and the scheme incorporates supply-chain requirements under the EU's Net Zero Industry Act.
The non-confidential version of the Commission's decision will be published under case number SA.118604 in the State aid register on the Commission's competition website once confidentiality issues have been resolved.
Why the Netherlands returned to subsidies
The approval marks the Netherlands' return to subsidised offshore wind procurement after a period in which tenders offering no subsidy failed to attract bids. The Dutch government increased the maximum subsidy for IJmuiden Ver Gamma-A from €0.104 to €0.117 per kilowatt-hour and for Gamma-B from €0.103 to €0.116 per kilowatt-hour, raising the total budget for the two farms from €7.896 billion to €9.456 billion, according to the Netherlands Enterprise Agency (RVO).
The IJmuiden Ver wind farm zone lies about 53 kilometres off the Dutch west coast in the North Sea and covers around 609 square kilometres across four sites, Alpha, Beta, Gamma-A and Gamma-B, with total capacity of about 6 gigawatts. Permits for the Alpha and Beta sites were issued in 2024.
What happens next
Developers can apply for a subsidy and permit for the new wind farms from 26 November to 10 December 2026. The Dutch government expects to grant the permits in the first quarter of 2027, with both wind farms expected to supply electricity from 2032.
The decision follows the Commission's approval on 10 November of a €2.04 billion Belgian scheme for the Princess Elisabeth offshore wind zone, as the EU uses state aid rules to accelerate offshore wind under its Clean Industrial Deal.
Frequently asked questions
Which wind farms does the €9.5 billion cover? IJmuiden Ver Gamma-A and Gamma-B in the North Sea, with 2 GW combined capacity and expected output of up to 7,441 GWh of renewable electricity a year.
When will the wind farms open? The tenders run before July 2027, permits are expected in the first quarter of 2027, and the farms are expected to supply electricity from 2032.
Sources: Offshore Source; Reuters via Devdiscourse.