HSBC sells $300m Oracle-linked data centre loan at steep discount as AI funding fears grow

By The Daily Byte ·17 Nov 2026 ·4 min read
The HSBC headquarters tower at Canary Wharf in London, showing the bank's name and red hexagon logo

HSBC has sold about $300 million of debt tied to a troubled Oracle-linked data centre project in New Mexico at a steep discount, in a deal that underlines growing unease among lenders about the financing of the artificial intelligence boom. Bloomberg first reported the sale, citing people familiar with the matter.

The bank sold its slice of an $18 billion financing package at prices in the mid-80s, meaning buyers paid roughly 85 cents for every dollar of face value. The sale took place several weeks ago, shortly after Oracle sent a notice to the project's developer citing force majeure, according to the report.

The debt helps fund construction of a vast data centre campus in Doña Ana County, New Mexico, known as Project Jupiter. The campus is designed to handle 2.45 gigawatts of computing capacity and forms a major part of the Stargate AI infrastructure build-out unveiled by US President Donald Trump in early 2025 alongside leaders from Oracle, OpenAI and SoftBank Group.

Why HSBC sold at a discount

Banks in a syndicated loan market are generally free to sell their stakes, but lenders holding construction project finance loans typically keep them on their balance sheets until a project is complete. Exiting early often means accepting a price below par, beyond the upfront fees earned on the loan.

HSBC's slice belonged to a package known as Project Miner, arranged in late 2025 by a syndicate of about 20 banks. The campus has been beset by regulatory hurdles and local opposition, including delays in securing the air and pipeline permits central to its plans.

Oracle sent the force majeure notice to the developer, a unit of Blue Owl Capital, in September, in an attempt to put off payments should the venture be derailed, Bloomberg had reported at the time. The notice came as the project faced mounting questions over its timetable and costs.

A wider chill in AI lending

The sale lands at a sensitive moment for AI infrastructure finance. Lenders are weighing their exposure to AI debt more carefully, and the market has been unsettled by the abrupt departure of Nvidia co-founder Jensen Huang and by renewed regulatory pushback following the Democratic sweep in the US midterm elections.

Finimize, also reporting the Bloomberg account, said the discounted sale showed banks wanted compensation for added uncertainty around the project. Other AI debt deals have also struggled: data centre operator QTS cut a debt sale from about $800 million to $300 million last week, according to credit market reports.

In London, banks were among the weaker sectors on Tuesday, falling 0.7%, as the FTSE 100 slipped ahead of Nvidia's quarterly results, according to Reuters. Investors have grown cautious about the pace and cost of the AI spending boom, and about how much of it is being funded with borrowed money.

What happens next

Attention now turns to whether other lenders in the Project Miner syndicate follow HSBC and sell down their exposure, and at what price. A wider sell-off would be a fresh signal that the market is repricing the risk of the largest AI infrastructure projects.

The project itself continues, with its backers still working through the permitting delays. But the price HSBC accepted suggests that, for at least one major bank, the risk of holding the loan to completion was no longer worth it. This article is not investment advice. HSBC, Oracle and Blue Owl Capital did not comment in the reports seen.

Frequently asked questions

How much debt did HSBC sell? About $300 million of a loan funding the Oracle-linked Project Jupiter data centre campus in New Mexico, sold at prices in the mid-80s, according to Bloomberg.

Why did HSBC sell at a discount? The sale came shortly after Oracle sent a force majeure notice to the project's developer, and the campus has faced regulatory delays and local opposition.

What is Project Jupiter? A 2.45-gigawatt data centre campus in Doña Ana County, New Mexico, part of the Stargate AI infrastructure programme, funded by an $18 billion loan package arranged by about 20 banks.