Long Thanh Airport Move Delayed by 34 Airlines

Thirty-four international airlines want to delay moving to Vietnam's new Long Thanh International Airport until the winter 2027 flight schedule or later, saying they need more time to prepare for the switch to the country's biggest new aviation hub.
The figure comes from a report by the Ministry of Construction to the Government on the conditions for putting the first phase of Long Thanh airport into operation. Of the 34 airlines, 24 are expected to move from the winter 2027 schedule, which starts in late October 2027, and 10 from the summer 2028 schedule or later.
The airlines are not opposed to the move. According to a survey by the Civil Aviation Authority, based on meetings and feedback at home and abroad, they support relocating to Long Thanh because of its modern infrastructure and capacity to meet growing demand. But moving to a new airport takes six to 12 months of planning, covering route networks, aircraft and crew allocation, ground services, ticketing systems and representative offices, and the airlines say they need that time.
Specialist cargo carriers face the same problem. International air logistics groups such as UPS, FedEx, Cargolux and DHL have strict requirements for express cargo terminals, customs facilities at warehouses, customs clearance corridors, parking positions, truck handling areas and transport connections, and preparations and technical assessments could take about 12 months.
Airport still set to open on 24 December
The airport itself is still scheduled to begin commercial operations at midnight on 24 December 2026, under the plan drawn up by its operator, the Airports Corporation of Vietnam (ACV). In the first phase, running to the end of the winter 2026 flight schedule on 27 March 2027, Long Thanh will prioritise the western concourse and the central area of the passenger terminal, with four check-in islands, and ACV expects to operate a maximum of about 366 flights a week, around 20 to 30 a day, including 322 domestic flights and 44 international flights. Vietnam Airlines and Vietjet Air will be the first two domestic carriers to operate there.
ACV has proposed a three-step transfer. From the opening until March 2027, airlines will be encouraged to operate international routes, including cargo, at Long Thanh according to demand. In the summer 2027 schedule, from March to October 2027, all long-haul international flights, including cargo, will move from Tan Son Nhat airport in Ho Chi Minh City. From the winter 2027 schedule, the remaining international flights will follow, except for short routes under 1,000 kilometres operated by Vietnamese airlines.
In the opening phase, Vietnamese airlines are ready to operate a number of flights under ACV's plan, including 72 flights a week from Vietnam Airlines and up to 294 a week from Vietjet, on domestic routes only.
Ministry says trial period is too short
The ministry also warned that the airport's trial programme has been short. Long Thanh is running an Operational Readiness, Activation and Transition (ORAT) programme of 55 scenarios in three phases from September to December. But measured from the start of integrated trial operations in late September to the planned start of commercial operations in late December, the period for comprehensive integrated testing is only about three months, and no actual flights have taken place.
For large, complex airports, the ministry said, preparation and testing usually take six to 12 months, with successive rounds to fix faults and test the systems again, citing trials at Beijing Daxing, Istanbul and Hong Kong that ran for months before opening.
"If Long Thanh International Airport begins operations while many items are still under construction or being completed, service quality for airlines and passengers could be affected, while the airport will also have to comply with very strict aviation security and safety regulations," the ministry said.
The ministry has asked ACV, as the airport operator, to review the opening plan in full and decide the timing, scope and operating plan based on completion, acceptance testing, trial operation and safety assessment. Opening on 24 December has the advantage of bringing the facility into use sooner, the ministry said, but the target needs to be reviewed against actual results.
The airlines have also asked for improvements to the wider airport system, including transit hotels of four stars or higher, high-quality medical services and convenient transport links to Ho Chi Minh City. Road links currently rely entirely on road transport, and the expressways and the An Phu interchange are under construction and are expected to be substantially completed by the beginning of the second quarter of 2027.
To attract airlines, ACV has also developed its own incentive programme, expected to cut some aviation service fees by 20 to 50 percent during 2026 and 2027.