Mozambique approves bigger Rovuma LNG plan ahead of decision

Mozambique's Council of Ministers has approved an amended development plan for the Rovuma LNG project, clearing a key regulatory hurdle before a final investment decision that ExxonMobil expects before the end of the year. The cabinet approved the revised plan on Tuesday 17 November.
The amended plan raises the onshore plant's planned capacity to 18.6 million tonnes of liquefied natural gas a year, up from the 15.2 million tonnes approved in 2019. The redesign replaces conventional processing units with modular, electrically powered equipment, which the National Petroleum Institute expects to cut emissions by about 40 per cent. A quarter of the gas produced is reserved for Mozambique's domestic market.
A near 30 billion dollar bet
Standard Bank estimates the development could cost nearly 30 billion US dollars, which would make it Mozambique's largest onshore energy project. The institute estimates the state could receive around 121 billion dollars over the plant's 25-year production life. Output could start in the early 2030s.
ExxonMobil agreed in October to raise its working interest in Rovuma LNG to 50 per cent through a deal with Eni, which will concentrate on floating LNG developments in Area 4 of the Rovuma Basin, including Coral Sul and Coral Norte.
Security and a second project advance together
Insurgent attacks in Cabo Delgado province forced workers to evacuate and delayed both onshore projects for years. A TotalEnergies-led group formally resumed work this year on the adjacent 20 billion dollar Mozambique LNG project, with capacity of 13.1 million tonnes a year. Together the two developments represent a combined investment pipeline of roughly 50 billion dollars in northern Mozambique.