Sterling Digital Bitcoin Mine Fully Live in West Texas

By The Daily Byte ·22 Nov 2026 ·3 min read
Rows of Bitcoin mining machines in a warehouse hall

Sterling Digital has brought its West Texas Bitcoin mine into full operation, mining more than two Bitcoin since the site started running as an integrated system on 24 October, at an estimated energy cost of about $19,400 per coin.

The AQSE-listed company, which trades under the ticker ASIC, announced on 17 November that its West Texas site, powered by its own gas generators, is fully operational. Low-cost natural gas is converted into electricity on site to power Bitcoin production directly at the source, putting the company's gas-to-power-to-Bitcoin model into operation for the first time.

A low-cost power model

The headline figure is the energy cost. During the initial operating period, Sterling estimated the energy cost attributable to mining at approximately $19,400 per Bitcoin. Vox Markets, reporting the announcement, put the estimated network-average energy cost per Bitcoin at about $50,000, meaning Sterling's figure is roughly 60% lower than the average miner's. Vox Markets also reported operational efficiency of more than 80% since full operations began.

At the centre of the site is an integrated system linking gas supply, power generation and the mining fleet. Sterling says the power generation, electrical infrastructure and mining equipment now operate as one system, so the energy used by the mining equipment is produced as part of the same operation rather than bought from the grid. The company uses modular infrastructure and what it describes as economically stranded natural gas in West Texas, where constrained gas markets create an opportunity to turn underused gas into computing power.

What the $19,400 figure does not cover

The $19,400 figure needs to be read carefully. It is an estimate, it covers the energy portion of mining costs only, and it relates to the early operating period. It does not include generator maintenance, equipment depreciation, staffing, insurance, site development, financing or corporate overhead, so it cannot be read as the total cost of producing a Bitcoin or as a profit margin. Sterling has also not disclosed the number of miners at the site, its hashrate or its power capacity, so the update centres on output so far and the first energy-cost estimate.

The economics also remain exposed to the Bitcoin price, over which the company has no control. The site had already produced its first verified Bitcoin during commissioning in September, when generators, electrical distribution, cooling and mining hardware were tested together. Full operations from 24 October marked the step from testing to continuous commercial mining.

Building a treasury

With the site live, Sterling has set out three operating priorities: reliable production, site optimisation and cost management. Those priorities serve two stated aims: building a Bitcoin treasury, a holding of mined Bitcoin kept by the company, and establishing an operating track record for the West Texas operation and its integrated system.

Chief executive Stefan Michaelides said: "Full operations at West Texas represent a significant milestone for Sterling and reflect the work of our team throughout development and commissioning." He added that the initial energy cost was encouraging and reinforced the importance of low-cost power to the company's strategy. Investors will now watch for later announcements on cumulative output, how the energy-cost estimate develops as the site runs longer, and how the Bitcoin treasury grows.