Vitol wins Tazama pipeline deal for Zambia fuel

By The Daily Byte ·21 Nov 2026 ·3 min read
TAZAMA fuel depot in Zambia with a tanker truck and loading gantry

Global energy trader Vitol has won the contract to build a new fuel pipeline between Tanzania and Zambia and to upgrade the ageing line that has linked the two countries since 1968. Vitol's Bahrain subsidiary was appointed project developer by TAZAMA Pipelines Ltd, the jointly owned operator, in a letter dated 6 November 2026, following a tender evaluation by the two governments.

Vitol Bahrain will finance, design, construct, commission and operate a new multi-product petroleum pipeline running roughly 1,710 kilometres from the Indian Ocean port of Dar es Salaam in Tanzania to Ndola, in Zambia's Copperbelt. The deal also covers financing, designing and overhauling the legacy TAZAMA pipeline, which was built in 1968. The project was approved by Zambia's cabinet in March.

What the project covers

Under plans outlined by Zambia's Ministry of Energy in September 2026, the new pipeline will transport up to seven million metric tons of refined petroleum products a year. Upgrading the existing line, including replacing the remaining eight-inch pipe sections with 12-inch pipe, will lift its capacity from 1.1 million metric tons to four million metric tons a year.

Once both are complete, the two pipelines could provide a combined annual capacity of 11 million tonnes. The original project specifications also provide for up to five fuel distribution points: Morogoro, Makambako and Songwe in Tanzania, and Mpika and Mkushi in Zambia.

Why it matters for Zambia

The existing TAZAMA pipeline currently moves about 800,000 metric tons of fuel a year, delivering roughly 3.6 million litres of diesel a day. That flow meets about 67 percent of Zambia's national diesel demand, making the corridor critical for a landlocked country heavily dependent on imported fuel.

Securing consistent fuel deliveries is especially important for the Copperbelt, where copper mining operations rely heavily on diesel to run heavy machinery, haul minerals and sustain industrial production. Expanding pipeline capacity should cut Zambia's reliance on road tankers, which are slower, costlier and harder on the road network.

Ownership and next steps

TAZAMA Pipelines Ltd remains jointly owned by the governments of Zambia, which holds a 66.7 percent stake, and Tanzania, which owns the remaining 33.3 percent. Vitol's appointment as project developer does not transfer ownership of the company, and the award does not grant Vitol any ownership stake in TAZAMA itself.