What Is a Section 106 Agreement? UK Guide

By The Daily Byte ·27 Nov 2026 ·10 min read
A new housing development under construction in England

A Section 106 agreement is a legal agreement between a developer and a local planning authority, made under section 106 of the Town and Country Planning Act 1990, which requires the developer to do something, or pay for something, as part of getting planning permission. It is also called a planning obligation, and it is the mechanism councils use to make sure a new development pays for the extra demands it creates, such as affordable housing, school places, roads or open space.

Section 106 agreements are common wherever new homes are built in England and Wales. If you are buying a new-build home, the chances are that a Section 106 agreement sits behind the development, and in some cases its terms affect you directly, for example by restricting who can buy or occupy the home. This guide explains what these agreements are, what they can require, the three legal tests they must pass, and what they mean for homebuyers.

What is a Section 106 agreement?

Planning obligations are legal obligations entered into to mitigate the impacts of a development proposal. That is how the government's planning guidance describes them. They can be made in two ways: a planning agreement under section 106 of the Town and Country Planning Act 1990, signed by a person with an interest in the land and the local planning authority, or a unilateral undertaking, entered into by the landowner alone without the council as a party.

A planning obligation can restrict how land is developed or used, require specified works to be carried out on the land, require the land to be used in a specified way, or require sums of money to be paid to the authority on specified dates or periodically. That is the wording of section 106 itself. The obligations run with the land, which means they bind future owners, not just the developer who signed them, and they are legally binding and enforceable.

Section 106 agreements are also commonly referred to as "section 106", "s106", and as developer contributions when considered alongside highway contributions and the Community Infrastructure Levy. They are not the same as planning conditions, which are attached to the planning permission itself, and they should only be used where a planning condition cannot address the impact in question.

The three legal tests

A planning obligation may only be a reason for granting planning permission if it meets three tests. The guidance states that obligations must be necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to the development. These tests are set out as statutory tests in regulation 122 of the Community Infrastructure Levy Regulations 2010, as amended, and as policy tests in the National Planning Policy Framework.

Necessary: the obligation must be needed to make the development acceptable in planning terms. If the development would be acceptable without it, the obligation cannot be justified.
Directly related: the obligation must relate to the development itself, not to some unrelated project elsewhere in the area.
Fairly and reasonably related in scale and kind: the size of the contribution must be proportionate to the size and impact of the development. A small scheme cannot be asked to fund a major piece of infrastructure on its own.

These tests matter because they limit what a council can demand. Planning obligations should never be used purely as a means of securing for the local community a share in the profits of a development, and money collected under an agreement should be used for the purpose for which it was collected. If contributions are made towards specific infrastructure that is not provided within an agreed timeframe, arrangements should be made for the contributions to be returned to the developer.

What do Section 106 agreements usually pay for?

The most common requirement is affordable housing. A council will often require a proportion of the homes in a development to be affordable housing, such as social rented homes or shared ownership homes, and the agreement sets the number, the tenure, and sometimes the timing. Other common requirements include financial contributions towards education, such as expanding a nearby primary school, highway improvements, public transport, healthcare facilities, open space and play areas, and measures to protect wildlife or manage flood risk.

On larger schemes the agreement may also require the developer to build community facilities, such as a community centre or a health centre, or to fund employment and training schemes for local people. The exact mix is set out in the council's local plan policies, which must be informed by evidence of infrastructure and affordable housing need and by a proportionate assessment of viability, so that the requirements can be accurately accounted for in the price paid for land.

The agreement is negotiated alongside the planning application, and it is usually completed before planning permission is granted. That timing matters: because the obligations are part of what makes the development acceptable, the permission and the agreement are linked, and the developer cannot lawfully start building until the agreement is in place.

Section 106, the Community Infrastructure Levy, and planning conditions

Three different tools can require a developer to contribute, and they are often confused. A Section 106 agreement is a negotiated, site-specific legal agreement tied to the impacts of one particular development. The Community Infrastructure Levy is a standard charge set by the council, calculated per square metre of new floorspace, which funds infrastructure across the whole area rather than one site. Planning conditions are requirements attached to the planning permission itself, such as the materials to be used or the hours of construction.

Section 106 agreement: negotiated, site-specific, tied to one development's impacts, can require works, restrictions or payments, runs with the land.
Community Infrastructure Levy: standard tariff per square metre, area-wide infrastructure funding, set by the council, not negotiated per site.
Planning condition: attached to the permission, controls how the development is built and used, cannot be used to secure financial payments.

In practice, a single development may be subject to all three. A council cannot use a Section 106 agreement to collect money for infrastructure that the Community Infrastructure Levy is already funding, and obligations should only be used where a planning condition cannot deal with the impact.

What does a Section 106 agreement mean for homebuyers?

For most buyers of new homes, a Section 106 agreement is invisible: the developer has already paid the contributions or built the required facilities, and the buyer simply benefits from the school places, roads or open space the agreement funded. But some agreements contain restrictions that affect the buyer directly, and those need to be checked before exchange of contracts.

The most important is an affordable housing restriction. Some homes are sold as affordable housing under a Section 106 agreement, which may limit the price at which the home can be resold, require the buyer to meet a local connection test, or restrict occupation to people who live or work in the area. Shared ownership homes are often secured this way. Your conveyancer should check the title and the agreement itself and explain any restriction to you, because the restriction binds future owners and can affect the price you can sell for.

Other restrictions can include a requirement that the home is occupied as a main residence rather than as a holiday home, or that a parking space or garage is kept with the property. If you are buying a home on a new development, ask your solicitor specifically whether a Section 106 agreement applies to the plot and what it requires. The agreement is a public document, registered against the title at the Land Registry, and your solicitor can obtain a copy.

Can a Section 106 agreement be changed?

Yes, but not easily. The agreement itself can be renegotiated voluntarily between the developer and the council at any time, and councils will consider changes where circumstances have changed, for example where a scheme has become unviable. There is also a formal route: under section 106A of the 1990 Act, a person bound by an obligation can apply to the local planning authority to modify or discharge it, normally after five years from the date the obligation was entered into. If the authority refuses, there is a right of appeal.

A separate procedure was introduced for affordable housing requirements. The Growth and Infrastructure Act 2013 inserted sections 106BA, 106BB and 106BC into the 1990 Act, creating an application and appeal procedure for reviewing planning obligations that relate to affordable housing where the requirement has made the scheme economically unviable. That procedure assesses viability only; it does not reopen other planning policy considerations or review the merits of the permitted scheme, and it does not apply where the permission was granted under a rural exceptions site policy.

Who enforces a Section 106 agreement?

The local planning authority enforces the agreement. A restriction or requirement imposed under a planning obligation is enforceable by injunction, and if there is a breach of a requirement to carry out works, the authority may enter the land, carry out the operations itself, and recover the cost from the person against whom the obligation is enforceable. Because obligations run with the land, enforcement can be taken against any person who derives title from the person who entered into the obligation, not just the original developer.

For residents, the practical route is to contact the council's planning enforcement team if a developer has not delivered something the agreement required, such as a play area or a footpath. Councils publish infrastructure funding statements that show what contributions have been received and spent, and these are a useful starting point if you want to know what a development near you was supposed to provide.

Frequently asked questions

Is a Section 106 agreement the same as the Community Infrastructure Levy? No. A Section 106 agreement is a negotiated agreement tied to one development. The Community Infrastructure Levy is a standard charge per square metre that funds infrastructure across an area.

Do Section 106 agreements affect house prices? They can. The cost of contributions is factored into the price the developer pays for land, and restrictions such as affordable housing limits can affect the resale price of an individual home.

Can a buyer see the Section 106 agreement? Yes. It is registered against the title at the Land Registry and your solicitor can obtain a copy. Ask specifically whether one applies to the plot you are buying.

How long does a Section 106 agreement last? Obligations can be unconditional or time-limited, and some are indefinite. A formal application to modify or discharge an obligation can normally be made after five years.

What happens if a developer breaks the agreement? The council can enforce it through the courts, including by injunction, and can carry out required works itself and recover the cost.

Sources: GOV.UK, Planning obligations (Planning Practice Guidance); legislation.gov.uk, Town and Country Planning Act 1990, section 106. This article is general information about planning law in England and Wales, not legal advice.