England housing crisis: 7,400 homes promised, 326 built

Three housing schemes in England promised 7,400 new homes between them. So far, only 326 have been built. That is the finding of a BBC investigation published on 23 November 2026, which visited stalled developments in Middlesbrough, York and Kent to ask why successive governments have failed to build enough homes.
The shortfall matters nationally. The government has set a target of building 1.5 million homes in England by the next election, and the BBC reports that the target will probably be missed. Net additional homes in England fell to 208,600 in 2024-25, down from 221,409 the previous year.
Middlesbrough: 2,400 homes promised, 216 built
In Middlesbrough, six horses graze on derelict land by the River Tees, close to the town centre. In 2004, the council announced plans to build 2,400 homes on that Middlehaven site, alongside a theatre, restaurants and hotels, in a development billed at £500 million. Twenty-two years later, just 216 homes have been built, and the council told the BBC the £500 million figure was simply an estimate of the overall cost — the money never existed.
In 2013 the scheme was proposed again, and the council bought 185 existing homes so they could be demolished to make space. Only 216 homes have been built to replace them, a net gain of 31. In September 2026, Middlesbrough Council announced plans for 462 new homes on the site, the start, it hopes, of a development of 3,400 homes in all. Middlesbrough Council says the first phase would deliver houses and low-rise build-to-rent apartments around the Old Town Hall.
York: 3,000 homes promised, none built
In York, a plan for 3,000 homes close to the historic city centre was announced in 2001. A quarter of a century later, not a single house has been built there. The project, York Central, stalled after the 2008 financial crash, before work had begun, and was held up for years by the cost of an access road to the site, which is surrounded by railway lines.
In September 2026 the first phase was finally given the green light. The National Railway Museum reports that City of York Council approved detailed plans on 10 September 2026 for 1,014 mixed-tenure homes, at least 20% of them affordable, with construction due to start next year and the first buildings ready in early 2029. The BBC reports that some 2,500 homes are planned by 2040, and that the whole scheme is now set to cost £2 billion.
Isle of Sheppey: 2,000 homes promised, 110 built
On the Isle of Sheppey in Kent, a development of up to 2,000 new homes was meant to help regenerate a deprived part of the island. It is now 23 years since the plan was first conceived, and only 110 houses have been built. The scheme was hailed in 2009 as a £400 million regeneration, but Swale Borough Council told the BBC the money never actually existed either. The plan was scaled back in 2015 to 1,180 homes, and even that reduced figure is unlikely to be achieved. The council has 1,800 households waiting for social housing, and a planned healthcare centre on the site remains unbuilt.
Why big schemes stall
Anthony Breach, director of policy and research at the Centre for Cities think tank, told the BBC that the UK relies on “large, complex schemes” to deliver new housing, so “when our larger sites get a bit stuck, that has a disproportionate impact on national housebuilding”. He also said the planning system is “pretty unusual internationally”, because local politicians can deny an application even when a developer has followed all the rules.
The pattern is not limited to the three sites visited. In Deptford, London, not one of the 3,500 homes planned for Convoy's Wharf has been built despite outline planning permission being given in 2005. At Barking Riverside, a 2008 plan for 10,800 homes stalled for years over poor transport links, but 3,000 homes have now been built since a new rail line opened, and plans have been approved to almost double the development to 20,000 homes.
A spokesperson for the Ministry of Housing told the BBC it was “working with Homes England to get stalled schemes moving, with housing starts up 20% on this time last year”, and that it had “unblocked and accelerated more than 130,000 homes” through its planning overhaul and £40 billion Social and Affordable Homes Programme.
Frequently asked questions
How many homes were promised across the three schemes? The three schemes in Middlesbrough, York and the Isle of Sheppey promised 7,400 homes between them. Only 326 have been built so far.
What is the government's housebuilding target? The government aims to build 1.5 million homes in England by the next election. The BBC reports that the target will probably be missed.
When will the first York Central homes be built? City of York Council leader Claire Douglas told the BBC the first houses should be built within two years, with construction starting next year.
Sources: BBC News (23 November 2026) and National Railway Museum (11 September 2026).