P3A Approves Two M-6 Motorway Sections Under PPP Model in Pakistan
By The Daily Byte
·19 Nov 2026
·4 min read

Pakistan's Public-Private Partnership Authority (P3A) Board has approved two sections of the Hyderabad-Sukkur M-6 motorway, spanning about 121 kilometres, for development through private investment. The decision was taken at the board's 46th meeting in Islamabad on Wednesday, 18 November 2026.
Sections I and II of the motorway will be offered under separate concession agreements. The selected investors will build and operate each stretch for 25 years, collecting tolls before returning the motorway to the National Highway Authority (NHA) in good condition.
## What the board approved
The meeting was chaired by Muhammad Ali, adviser to the prime minister on privatisation and chairman of the Privatisation Commission. The government will provide viability-gap funding for Section I to improve its commercial feasibility and help keep tolls affordable. No such funding was announced for Section II.
The NHA, advised by the Asian Development Bank, will invite bids from qualified domestic and international investors for the two sections. The full M-6 is planned as a six-lane, access-controlled motorway of around 306 kilometres, divided into five sections.
## A shorter journey between Hyderabad and Sukkur
Once completed, the motorway is expected to reduce travel time between Hyderabad and Sukkur from roughly six hours to about three. At present, traffic relies on the busy N-5 national highway, where freight vehicles share the road with local traffic through towns and settlements.
P3A Chairman Muhammad Ali said the project would complete a key link in Pakistan's motorway network. Officials expect the route to improve freight movement between Karachi's ports, industrial areas, agricultural regions and markets further north. The PPP approach also assigns maintenance responsibilities to private operators during the concession period, while allowing the government to share in project revenues.
## The five sections of the M-6
The two approved sections cover the Hyderabad to Nawabshah stretch of the route. According to an earlier briefing by the NHA to a National Assembly committee, Section I runs 57 kilometres from Hyderabad to Tando Adam at an estimated cost of Rs81 billion, while Section II runs 63 kilometres from Tando Adam to Nawabshah at an estimated cost of Rs70 billion.
The remaining three sections, between Nawabshah and Sukkur, are being financed through loans from the OPEC Fund and the Islamic Development Bank and are in the procurement process. The Islamic Development Bank has signed a $475 million loan agreement for Sections IV and V, while the OPEC Fund board has approved $230 million for Section III.
## The last missing link
The M-6 is the only missing link in Pakistan's north-south motorway network, which runs from the port city of Karachi through Sindh and Punjab and finally terminates in Peshawar. The project has been discussed for many years, but delays, financing issues and procurement problems have repeatedly held it back.
The government has said the revised project cost of Rs364 billion has already been approved by the Executive Committee of the National Economic Council, and that land acquisition for the main motorway corridor has been completed. Procurement for the three sections financed by international lenders is at different stages, with bids for Section III received in September and under evaluation.
## Frequently asked questions
**What is the M-6 motorway?**
The M-6 is a planned 306-kilometre, six-lane motorway between Hyderabad and Sukkur in Sindh, the last missing link in Pakistan's north-south motorway network.
**How long will the Hyderabad-Sukkur journey take on the M-6?**
Travel time is expected to fall from roughly six hours on the N-5 to about three hours once the motorway is complete.
**Who will build the first two sections?**
Sections I and II will be built and operated by private investors under separate 25-year concession agreements, with the NHA inviting bids with advice from the Asian Development Bank.
Sources: Abb Takk News reported the P3A board's approval of the two sections at its 46th meeting; Khabr.pk also reported the approval, citing Express News and 24 News Business.