PTA Inspects 226 Mobile Sites, Finds Power Faults

The Pakistan Telecommunication Authority inspected 226 mobile network sites across the country between 29 October and 11 November 2026, uncovering faulty batteries, failing generators, unreliable electricity supplies and safety risks involving fibre-optic cables, the Associated Press of Pakistan reported on 20 November.
The exercise is part of the regulator’s nationwide field monitoring programme, which aims to strengthen the quality and reliability of telecom services. The inspections were carried out in coordination with district administrations, elected representatives, local stakeholders and telecom operators, so that the deficiencies found can be identified and fixed rather than simply recorded.
Sixteen cities and regions covered
The monitoring covered Karachi, Lahore, Bahawalpur, Quetta, Rawalpindi, Islamabad, Pindi Gheb, Charsadda, Peshawar, Mirpur, Skardu, Kharmang, Haripur, Mansehra, Gwadar and Sargodha. The list runs from the high-altitude districts of Gilgit-Baltistan and Azad Jammu and Kashmir to the Balochistan coast, showing that the sweep went well beyond the big cities where most subscribers live.
With the latest round, the cumulative number of mobile sites monitored by the authority has risen to more than 1,127. The programme has been running in successive rounds through the autumn, with 184 sites inspected between 22 and 28 October, taking the total past 900, and 166 sites checked between 15 and 22 October.
What inspectors found
The key findings were power supply and backup redundancy problems, equipment deficiencies, battery and generator faults, fibre-optic cable safety concerns, and other administrative and infrastructure-related shortcomings. Backup power matters because a mobile site must keep working when the mains supply fails; a dead battery or a generator that will not start can take a whole neighbourhood off the network, dropping calls and cutting data exactly when people need it most.
Fibre-optic safety was also flagged, alongside equipment shortfalls at the sites visited. The authority did not name individual operators or publish site-by-site results in its statement, and it did not say how many of the 226 sites had each type of fault.
A rolling inspection programme
The authority said it is pursuing corrective measures through sustained field monitoring and coordinated engagement with the relevant stakeholders, with the aim of improving the reliability, resilience and overall quality of telecom services across the country. The inspections are continuing, and the findings from each round feed into the next, so operators know which sites the regulator has already visited and what it expects to be fixed.
For subscribers, the exercise is a reminder that mobile quality depends on more than spectrum and handsets. Towers need working batteries, fuelled generators and properly installed fibre, and the regulator’s latest round found weaknesses in all three areas at sites across Pakistan.