RAF Brize Norton runway rebuilt in 16 weeks

Aircraft have returned to RAF Brize Norton after the station's 3km runway was fully replaced in just 16 weeks, the Defence Infrastructure Organisation (DIO) has announced.
The first aircraft touched down on the new runway on Friday, 13 November, and the DIO has now formally handed the runway back to the RAF. The work is the headline element of a wider 180 million pound programme to overhaul critical airfield infrastructure at the Oxfordshire base.
Brize Norton is the RAF's main air transport hub, and the runway is the station's only one. Rebuilding it while keeping the base's aircraft flying meant dispersing the fleet to several alternative locations for the 16-week construction period, so operations could continue while the old surface was dug up and replaced.
Who built it, and what it is made of
Working with Air Infrastructure, the DIO appointed VolkerFitzpatrick to deliver the works, with AECOM providing technical services throughout the project. The DIO handed the finished runway to Air Commodore Phil Reid, Head of Air Infrastructure, who received it on behalf of the RAF.
The new runway has been constructed using Pavement Quality Concrete and Grooved Marshall Asphalt. The DIO says those materials were chosen to improve the runway's resilience to higher temperatures and the effects of climate change, and that the concrete is expected to more than double the runway's service life compared with the materials used before.
Mike Green, chief executive of the DIO and director general for infrastructure in the National Armaments Director Group, said: "This has been a tremendous team effort. Delivering at pace while maintaining our focus on the RAF's operational needs is no small achievement. The collaboration between DIO, the RAF and our contractors has been outstanding, and the result speaks for itself."
More work to come before 2027
The runway is only one part of the wider programme. Work continues on refurbishing taxiways and associated infrastructure, upgrading airfield lighting systems, and improving drainage and supporting infrastructure, with overall project completion expected late in 2027.
Air Commodore Reid said the work would strengthen the airfield's long-term strategic and operational capabilities, safety and resilience, adding: "This success has only been achieved with tremendous team effort, which will continue through to overall project completion late in 2027."
Bob Noyes, the DIO's principal project manager, said: "After an incredibly busy 16 weeks, it is fantastic to see aircraft returning home to RAF Brize Norton and using the new runway. I am proud of the immense teamwork that has gone into delivering this major element of the programme in such a short period, supporting the Station's vital role in military operations around the world."
The programme is funded through the Defence Investment Plan, which includes investment in refurbishing major runways and renewing critical infrastructure across the defence estate. The DIO says the new runway will keep the station fully operational and fit for decades to come, while delivering long-term value for money.