World Bank Downgrades Punjab GRADES Project

The World Bank has slightly downgraded its $150 million education project in Punjab, citing technical assistance that has not yet been mobilised and baseline data that remains unavailable, even though the project has made substantial progress against several of its targets.
In its latest public disclosure, the Bank cut the project's overall implementation progress rating from "satisfactory" to "moderately satisfactory". It left the rating for progress towards the project's development objectives unchanged at "moderately satisfactory" and kept the overall risk rating at moderate.
Why the rating was cut
The Bank said technical assistance supporting several reform deliverables has not yet been mobilised, and baseline data for the project remains unavailable. Both gaps will be addressed during a restructuring of the project, the Bank said, adding that the formal restructuring to reflect the government's revised construction plan remains an important next step.
The Bank warned that continued progress on those arrangements, alongside the start of classroom construction, will be important to sustain implementation and achieve the project's intended results.
The targets that are being met
The disclosure also records progress. The project has met its financial targets for the previous fiscal year, and progress has been recorded across its performance-based conditions, according to the Bank.
Enrolment in public-private partnership schools has increased substantially from the project baseline, with the year-four target achieved ahead of schedule. In addition, 1,092 more schools now provide early childhood care and education that meets quality standards.
Classroom construction has not begun
Classroom construction has yet to begin, although preparatory activities have progressed, the Bank said. The construction component, worth about $82 million, is the largest part of the project, and its delay is one of the reasons the restructuring is needed.
The project, known as Getting Results: Access and Delivery of Quality Education Services in Punjab, or GRADES, was approved by the Bank's executive directors in June 2024, with a closing deadline of June 2029.
What the project is meant to do
GRADES aims to increase participation rates for girls and boys in pre-primary and primary grades and to improve reading proficiency in the early grades. It was designed to improve learning outcomes, recover from learning losses during the COVID-19 pandemic, strengthen school management and expand school participation.
It is expected to benefit about five million children, 7,000 headteachers, 165,000 teachers and more than 3,000 teacher mentors in public schools and Punjab Education Foundation schools. Project documents reported that, as of June 2024, more than seven million children in Punjab were out of school, a number the project was expected to help the provincial government reduce substantially.
The next test for the project is whether the restructuring is completed, the technical assistance is mobilised and classroom construction starts. Until then, the Bank's message is mixed: the targets that depend on enrolment and school management are moving, but the building work and the data needed to measure progress are still waiting.