Queen's Hospital £42m A&E rebuild work begins

Work begins this month on a £42 million rebuild of the accident and emergency department at Queen's Hospital in Romford, after the government confirmed the funding following a 22-month campaign by the hospital trust.
The money is the largest single award in a £140 million winter fund for urgent care announced by the Department of Health and Social Care on 18 October, covering 14 schemes across England. Queen's alone takes about 30% of the fund.
Barking, Havering and Redbridge University Hospitals NHS Trust, which runs Queen's, called the award a “landmark moment” when it was announced. Its interim chief executive, Fiona Wheeler, said in the trust's November board report that work begins this month, with a detailed plan to complete the rebuild by the summer of 2029.
Built for 325 patients a day, now seeing twice that
The department opened with the hospital in 2006 and was built for about 325 patients a day. It now regularly sees more than twice that number, according to the trust, and is one of the worst designed departments of its kind in the country.
Patients currently have to walk 335 steps from the hospital entrance to the adult A&E. Once the rebuild is complete, that will fall to 50 steps.
The new department will include a new waiting room, dedicated resuscitation areas, and private zones where patients can “decompress”. A transformed children's A&E is also to be built, alongside a new digital system for the department. Healthcare innovations company UCL Partners will assist the trust with designing the digital system.
Nine phases, children's A&E in 2027
The rebuild has been split into nine phases. The first three focus on enabling works, including adding a ventilation plant on the roof, to be completed by next summer.
Work then switches to building the new children's A&E in phase four, which should be finished by the autumn of 2027 and will include an additional children's mental health space.
Nothing changes for patients yet: the existing A&E continues to operate as it does now until building work starts.
Performance improving, trust says
The board report also records recent performance gains. In September, more than four out of five patients seeking urgent and emergency care — 81.7% — were admitted, discharged or transferred within four hours, and the trust says it is confident of hitting the NHS target of 82% by next March.
The number of people being cared for in A&E corridors fell by 25% over June to August compared with the same period last year.
Sources: Barking, Havering and Redbridge University Hospitals NHS Trust, Chief Executive's Board Report, November 2026 and Nursing Times.