Tarbela 5 Cost Soars to Rs316bn After Tunnel Flooding

The cost of Pakistan's Tarbela 5th Extension hydropower project has risen from about Rs82.36 billion to Rs316.41 billion, an increase of roughly 284 percent, while completion has slipped from January 2021 to June 2028. The latest setback came on 9 November 2026, when water flooded a tunnel and the powerhouse area under construction, halting work indefinitely.
The revised cost was authorised in a Planning Commission office memorandum issued on 2 November 2026, just seven days before the flooding. The 1,530-megawatt project converts Tarbela Dam's fifth irrigation tunnel into a power tunnel, adding three 510-megawatt units and lifting the dam's installed capacity from 4,888 megawatts to 6,418 megawatts. The World Bank is lending $390 million towards the project and the Asian Infrastructure Investment Bank $300 million.
Two floods in fifteen months
The November flooding was the second time in fifteen months that water has broken into the construction works. In August 2025, rising reservoir levels flooded parts of the site and a downstream cofferdam collapsed, stopping construction. A three-member inquiry found that a flood did not cause that collapse, and pointed to unauthorised design changes: the contractor proposed replacing the approved roller-compacted design with a rock-filled structure the contract did not allow, the consultant accepted it conditionally, and WAPDA approved it late.
The cause of the 9 November incident remains disputed. WAPDA has said a weak section of rock collapsed during excavation of the second bench connecting tunnel, letting water from an intake pit surge into the tunnel and the powerhouse area. The Haripur district administration has instead pointed to a breach in a protective bund. One worker was swept away in the flooding and rescued, and no damage was reported to the main tunnel, powerhouse, tailrace culvert or switchyard, or to the main dam itself.
Questions over oversight
The project's troubles have drawn scrutiny from Pakistan's top project sanctioning bodies. The Central Development Working Party and the Executive Committee of the National Economic Council ordered a review of WAPDA's handling of the project and instructed that a committee led by the water resources minister examine procedural lapses and delays. According to official documents reported in November, the Planning Commission asked the Water Resources Ministry to set up the committee in June, but it had still not been formed.
The Auditor-General has also recorded concerns about the project, including a Rs3,269.7 million direct award to the supervising consultant, MM Pakistan, the lowering of key-expert criteria, and a conflict of interest involving the chairman of the Pakistan Engineering Council, who has been recorded as a co-owner of the consultant firm.
Planning Commission documents warn that the economics of the project are now in question. The estimated cost of generation could reach Rs27 to Rs28 per unit over 30 years, and expected annual energy output has fallen to about 1.347 billion units against 1,810 gigawatt-hours originally planned, a loss of roughly a quarter. The World Bank loan closes on 30 September 2027, nine months before the revised completion date of June 2028.
What happens next
Work on the extension remains suspended while the damage is assessed. The project was listed in the government's power plan for first power from its units between September and December 2026, a timetable that now looks unachievable. An independent root-cause review of the November flooding has been called for by commentators, along with accountability for the decisions that preceded it. Dawn's business pages returned to the project on 23 November 2026 under the heading "Big dams, bigger liabilities", reflecting how the extension has become a symbol of cost overruns in Pakistan's hydropower programme.
Frequently asked questions
How much has the Tarbela 5 project cost risen? From about Rs82.36 billion in the original PC-I to Rs316.41 billion in the revised approval of 2 November 2026, an increase of roughly 284 percent.
When will Tarbela 5 be completed? The revised target is June 2028, against an original schedule of January 2021.
What happened on 9 November 2026? Water flooded a tunnel and the powerhouse area under construction, halting work indefinitely. WAPDA blamed collapsing weak rock; the Haripur district administration pointed to a breached protective bund.
Sources: The Scoop, reporting the Planning Commission memorandum, cost figures and inquiry findings; The Newswire, reporting the 9 November flooding and the suspension of work. Published 23 November 2026.